The Cabinet has just approved emergency legislation to allow for extensions of planning permissions, primarily for housing developments, for an additional three years. The intention is to have this legislation passed before the summer recess.
- Purpose: The main goal is to activate delayed housing developments and prevent planning permissions from lapsing and to boost housing supply.
- Extension Period: Developers can apply for an extension of up to three years.
- Eligibility and Conditions:
- Applications must be made within six months of the legislation commencing.
- Construction must begin within 18 months of the legislation passing.
- The extensions are aimed at permissions nearing expiry where work has not yet started.
- Judicial Review Impact: The time spent in judicial review will not count against the original planning permission duration, preventing permissions from expiring due to these delays. This will apply retrospectively to permissions that have gone through or are currently in Judicial Review.
- “Use It or Lose It” Principle: While extensions are being granted, the government insists on a “use it or lose it” approach, requiring developments to commence within the specified 18-month timeframe.
- Scale of Impact: It’s estimated that around 15,000 residential units in Dublin alone, across 265 inactive sites, have permissions due to expire within the next two years. Additionally, almost 19,000 units on 52 sites have been subject to judicial review over the last five years, with many of those permissions having their effective duration eroded.
- Political Context: The legislation is a response to concerns about the slow pace of housing delivery and aims to unlock stalled projects. It has some cross-party support, though concerns about land hoarding and the root causes of planning delays (like under-resourcing of planning bodies) have also been raised.